Training schedules for all squads UPDATED

Gateshead Council's 'Building a Better Future' programme of new pool builds and pool refurbishments continues in 2010.

Below is a summary of the latest known schedule for the pools programme.

 

1.            Birtley Closes September 5th

 

September 5th, we lose all Birtley time .. there will be no like-for like compensatory time.

 

By way of compensation, we gain an extra morning and an extra session on Saturday morning.

 

2.            4 Lane Blaydon Pool will close on 3rd October and re-open as 6 Lane Blaydon Leisure Centre on 4th October.

 

3.            The provisional date for the closure of 6 lane Felling Pool is end of October with it re-opening as 4 lane Heworth Leisure Centre at the start of November. There will not be a gap between Felling closing and Heworth opening.

 

Note that because Felling shrinks to 4 lanes, squads that trained together in the old pool, no longer fit together in the new pool.

 

4.            The provisional date for Dunston re-opening is the start of January

 

5.            The provisional date for Birtley re-opening is the end of March.

CHANGE OF SWIM PROGRAMME SEPTEMBER 2010 to DECEMBER 2010

Unfortunately due to the number of changes that occur over the next 4 months it is not possible to display the training schedule on screen.  Please click the following link to access a PDF version of the schedules

 Swim Times September 2010 Version 8

Note these schedules are subject to change. Swimmers/Parents/Coaches will need to be diligent in reviewing available sessions almost on a week by week basis. For example dates for Felling closure and Heworh re-opening is not yet firm.


http://www.gawswim.org.uk/index.php/1202